AGS Checkout Schedule FY05

 

November 2004

 

Sun

Mon

Tue

Wed

Thu

Fri

Sat

1

  • Sweep AGS, Get all water systems turned on.
  • Remove Summer and restricted access LOTO..
  • Remove LOTO from Booster.
  • Prepare for DRY run in Booster (load files etc.).
  • HI POT AGS.
  • Begin 5.22.a Power supply check out for AGS.
  • Energize BTA for diagnostic study (continue as necessary throughout the week).

2

        Turn on power supplies for heat run.

        Begin 5.21 attachments a; AGS wall monitor checkout,

  • b AGS loss monitor checkout,
  • e movable apertures checkout (as needed),
  • g tune meter checkout (AGS).
  • h; LTB/BTA instrumentation checkout. Continue OPM 5.22.a and Booster dry run as necessary.

3

        Begin OPM 5.23a AGS RF checkout.

  • Address outstanding problems from beginning of the week
  • Address RSC checklist outstanding items.
  • Conduct any rollup activity needed in the AGS.
  • Sweep U line berm, U upstream, A target and Switchyard.
  • Have CAS secure necessary shield tops (OPM 6.1.9.a)

4

  • Complete AGS checkout. Address any interlocks.
  • Complete RSC checklists.
  • Load files, supercycles etc. for Cu and
  • make all other preparations for AGS dry run.

5

AGS DRY run.

6

B

E

A

M

?

 

 